Wallace Solar I

Project Description: Wallace Solar I is a 107.4 MWdc / 74 MWac single-axis tracking solar facility in Aiken County, South Carolina, interconnecting to Santee Cooper at 115 kV.

As part of our commitment to responsible development and the Equator Principles, we completed a series of environmental and cultural reviews for the project site as follows:

Environmental Site Review

A Phase I Environmental Site assessment (ESA) conducted in accordance with ASTM E1527-21 standards identified no Recognized Environmental Conditions.

Wildlife

A suitable habitat assessment conducted on-site determined that the project will have no effect on any threatened or endangered species. The U.S. Fish and Wildlife Service provided concurrence based on these results.

Cultural Resources

A desktop review and on-site surveys performed by a licensed archaeologist identified no historic or cultural resources. The South Carolina Historic Preservation Office concurred with these results.

Wetlands

A wetland delineation was reviewed and U.S. Army Corps of Engineers provided concurrence. The project will not impact any wetland features.

Community Engagement

energyRe engaged Aiken County, landowners, and the public through noticed, ADA-compliant meetings, calls, and emails, and coordinated with county staff to meet permit requirements. No issues are known. Concerns may be directed to Aiken County, SCDES, or the energyRe project team.

Human Rights

energyRe’s Code of Conduct and Business Ethics, incorporated into its module supply agreements, requires suppliers to commit to “eliminating all forms of forced or compulsory labor” and “not employing children.” The EPC Agreement prohibits “any Equipment manufactured using forced labor.”

Climate Resilience

The project was engineered to site-specific design parameters for wind, rainfall, and flood conditions, with additional operational measures for hail and wildfire. Trackers move to a 60° hail stow position when severe hail is forecast and are rated for maximum expected winds on site. Inverters, major equipment, and modules sit above 100-year flood depths, and a Wildfire Mitigation Plan and Withstand Program are in place.